Citation: | Huang Jianhua, Bao Feng, Wang Yunchen, Li Hong. Influence of ground-surface deformation in pipe jacking construction with parallel differential section[J]. Bulletin of Geological Science and Technology, 2021, 40(6): 185-192. doi: 10.19509/j.cnki.dzkq.2021.0618 |
[1] |
荣亮, 杨红军. 郑州市下穿中州大道超大断面矩形顶管隧道施工沉降控制技术[J]. 隧道建设, 2015, 35(12): 1338-1344. doi: 10.3973/j.issn.1672-741X.2015.12.016
Rong L, Yang H J. Settlement control technology for tunnel crossing underneath Zhongzhou zvenue in Zhengzhou constructed by super-large rectangular cross section pipe-jacking machine[J]. Tunnel Construction, 2015, 35(12): 1338-1344(in Chinese with English abstract). doi: 10.3973/j.issn.1672-741X.2015.12.016
|
[2] |
唐培文. 大断面矩形顶管减阻技术应用研究: 以苏州综合管廊矩形顶管为例[J]. 地质科技通报, 2020, 39(2): 198-203. doi: 10.19509/j.cnki.dzkq.2020.0222
Tang P W. Application of drag reduction technology of large section rectangular pipe jacking: A case study of rectangular jacking of Suzhou comprehensive pipe rack[J]. Bulletin of Geological Science and Technology, 2020, 39(2): 198-203(in Chinese with English abstract). doi: 10.19509/j.cnki.dzkq.2020.0222
|
[3] |
王道伟, 王福芝, 黎轩, 等. 水平平行顶管相互影响试验研究[J]. 地质科技情报, 2016, 35(2): 71-74. https://www.cnki.com.cn/Article/CJFDTOTAL-DZKQ201602017.htm
Wang D W, Wang F Z, Li X, et al. Experimental study on influence between horizontal parallel pipe jacking[J]. Geological Science and Technological Information, 2016, 35(2): 71-74(in Chinese with English abstract). https://www.cnki.com.cn/Article/CJFDTOTAL-DZKQ201602017.htm
|
[4] |
李博, 许烨霜, 马磊, 等. 平行顶管近接施工的室内试验研究[J]. 地下空间与工程学报, 2014, 10(1): 67-71, 155. https://www.cnki.com.cn/Article/CJFDTOTAL-BASE201401011.htm
Li B, Xu Y S, Ma L, et al. Laboratory investigation on effects of nearby construction of parallel pipe-jacked tunnels[J]. Chinese Journal of Underground Space and Engineering, 2014, 10(1): 67-71, 155(in Chinese with English abstract). https://www.cnki.com.cn/Article/CJFDTOTAL-BASE201401011.htm
|
[5] |
Chapman D N, Ahn S K, Hunt D V. Investigating ground movements caused by the construction of multiple tunnels in soft ground using laboratory model tests[J]. Canadian Geotechnical Journal, 2007, 44(6): 631-643. doi: 10.1139/t07-018
|
[6] |
李明宇, 王松, 张维熙, 等. 大断面矩形顶管隧道施工引起的地面沉降分析[J]. 铁道建筑, 2019, 59(5): 81-84. https://www.cnki.com.cn/Article/CJFDTOTAL-TDJZ201905019.htm
Li M Y, Wang S, Zhang W X, et al. Analysis of ground subsidence caused by construction of large section rectangular pipe jacking tunnel[J]. Railway Engineering, 2019, 59(5): 81-84(in Chinese with English abstract). https://www.cnki.com.cn/Article/CJFDTOTAL-TDJZ201905019.htm
|
[7] |
周浩, 周千淼, 谈力昕, 等. 考虑注浆作用的矩形顶管竖向土压力计算模型[J]. 地质科技通报, 2021, 40(2): 125-130. doi: 10.19509/j.cnki.dzkq.2021.0201
Zhou H, Zhou Q M, Tan L X, et al. Vertical soil pressure calculation model of rectangular box jacking considering grourting effect[J]. Bulletin of Geological Science and Technology, 2021, 40(2): 125-130(in Chinese with English abstract). doi: 10.19509/j.cnki.dzkq.2021.0201
|
[8] |
Ocak I. A new approach for estimating the transverse surface settlement curve for twin tunnels in shallow and soft soils[J]. Environmental Earth Sciences, 2014, 72(7): 2357-2367. http://www.onacademic.com/detail/journal_1000036499491710_dc83.html
|
[9] |
Wang H, Qin W M, Jiao Y Y. Stability assessment for highway with large-span box culvert jacking underneath: A case study[J]. Canadian Geotechnical Journal, 2013, 50(6): 585-594. http://www.onacademic.com/detail/journal_1000036846039010_dd3c.html
|
[10] |
Chen R P, Zhu J, Liu W, et al. Ground movement induced by parallel EPB tunnels in silty soils[J]. Tunnelling and Underground Space Technology Incorporating Trenchless Technology Research, 2010, 26(1): 163-171. http://www.researchgate.net/profile/Wei_Liu146/publication/222218007_Ground_movement_induced_by_parallel_EPB_tunnels_in_silty_soils/links/561dd29f08ae50795afd8421.pdf
|
[11] |
Zhang D W, Liu B, Qin Y J. Construction of a large-section long pedestrian underpass using pipe jacking in muddy silty clay: A case study[J]. Tunnelling and Underground Space Technology Incorporating Trenchless Technology Research, 2016, 60: 151-164. http://www.onacademic.com/detail/journal_1000039535991010_ef0c.html
|
[12] |
Ren D J, Xu Y S, Shen J S, et al. Prediction of ground deformation during pipe-jacking considering multiple factors[J]. Applied Sciences, 2018, 8(7): 1051. http://www.researchgate.net/publication/326021197_Prediction_of_Ground_Deformation_during_Pipe-Jacking_Considering_Multiple_Factors/fulltext/5b344cbca6fdcc8506d6f978/326021197_Prediction_of_Ground_Deformation_during_Pipe-Jacking_Considering_Multiple_Factors.pdf?origin=publication_detail
|
[13] |
银英姿, 赵强, 崔芳静, 等. 土压平衡矩形顶管施工引起的地表沉降探究[J]. 长江科学院院报, 2019, 36(1): 95-101. https://www.cnki.com.cn/Article/CJFDTOTAL-CJKB201901023.htm
Yin Y Z, Zhao Q, Cui F J, et al. Ground subsidence caused by earth pressure balanced rectangular pipe jacking construction[J]. Journal of Yangtze River Scientific Research Institute, 2019, 36(1): 95-101(in Chinese with English abstract). https://www.cnki.com.cn/Article/CJFDTOTAL-CJKB201901023.htm
|
[14] |
郝小红, 郭佳. 考虑超大断面顶管施工过程的地层变形数值分析[J]. 华北水利水电大学学报: 自然科学版, 2017, 38(6): 66-71, 81. https://www.cnki.com.cn/Article/CJFDTOTAL-HBSL201706010.htm
Hao X H, Guo J. Numerical analysis of stratum deformation considering large section pipe jacking construction process[J]. Journal of North China University of Water Resources and Electric Power: Natural Science Edition, 2017, 38(6): 66-71, 81(in Chinese with English abstract). https://www.cnki.com.cn/Article/CJFDTOTAL-HBSL201706010.htm
|
[15] |
Shen S L, Cui Q L, Ho C E, et al. Ground response to multiple parallel micro tunneling operations in cemented silty clay and sand[J]. Journal of Geotechnical and Geoenvironmental Engineering, 2016, 142(5): 04016001. http://smartsearch.nstl.gov.cn/paper_detail.html?id=55d1c0be99b59a019e33019706eb5ab5
|
[16] |
Bao X K, Liang L J. Numerical modeling research of rectangle pipe-jacking construction[J]. Applied Mechanic and Materials, 2014, 3306: 921-924. http://www.onacademic.com/detail/journal_1000038089908010_3229.html
|
[17] |
He C, Feng Y, Fang Y, et al. Surface settlement caused by twin-parallel shield tunnelling in sandy cobble strata[J]. Journal of Zhejiang University-Science A: Applied Physics and Engineering, 2012, 13(11): 62-73. http://d.wanfangdata.com.cn/Periodical_zjdxxb-e201211007.aspx
|
[18] |
Yen J, Shou K. Numerical simulation for the estimation the jacking force of pipe jacking[J]. Tunnelling and Underground Space Technology, 2015, 49(6): 218-229. http://www.onacademic.com/detail/journal_1000037790009010_2cef.html
|
[19] |
齐培林. 并行矩形顶管施工力学与相互影响研究[D]. 武汉: 武汉科技大学, 2018.
Qi P L. Research of construction mechanics and interaction of parallel rectangular pipe-jacking[D]. Wuhan: Wuhan University of Science and Technology, 2018(in Chinese with English abstract).
|
[20] |
陈月香. 超大矩形断面顶管减摩注浆作用机理及优化设计研究[D]. 福州: 福建工程学院, 2019.
Chen Y X. Study on antifriction grouting mechanism and optimum design of super-large rectangular section pipe jacking[D]. Fuzhou: Fujian University of Technology, 2019(in Chinese with English abstract).
|
[21] |
葛春辉. 顶管工程设计与施工[M]. 北京: 中国建筑工业出版社, 2011.
Ge C H. Pipe jacking engineering design and construction[M]. Beijing: China Architecture & Building Press, 2011(in Chinese).
|
[22] |
张凯, 武永新, 田润泽. 并行顶管不同纵向间距下施工数值模拟分析[J]. 地下空间与工程学报, 2020, 16(增刊2): 835-840. https://www.cnki.com.cn/Article/CJFDTOTAL-BASE2020S2044.htm
Zhang K, Wu Y X, Tian R Z. Numerical simulation analysis on parallel pipe jacking under different longitudinal spacing[J]. Chinese Journal of Underground Space and Engineering, 2020, 16(S2): 835-840(in Chinese with English abstract). https://www.cnki.com.cn/Article/CJFDTOTAL-BASE2020S2044.htm
|
[23] |
张振. 超大矩形断面顶管隧洞开挖引起的地表沉降研究[D]. 郑州: 华北水利水电大学, 2016.
Zhang Z. Research of surface subsidence caused by the large rectangular pipe jacking tunnel excavation[D]. Zhengzhou: North China University of Water Resources and Electric Power, 2016(in Chinese with English abstract).
|